This Week

Slab3

K8 Schoolhouse:

  • Prepping for installation of steel columns and beams.
  • Framing interior walls.
  • Curing* concrete for K8 slab-on-grade.

Gym: Pouring foundation walls.

Dorm: Installing fire alarm and fire sprinkler.

Submitting documents for natural gas permit.