This Week

K8_Roof Dry-in_small

K-8 Schoolhouse:

  • Roof “dry-in” (see above), readying the school for for MEP (mechanical, electrical, plumbing) installations.
  • Mechanical duct work has begun

Gym: Wall and roof framing, with installation of structural insulated panels (SIPs).

Dorm: Drywall taping and finishing.

Campus: Water farm excavation and installation begins.