This Week

Last Truss

K-8 Schoolhouse:

  • air handling unit being installed.
  • framing and roof sheathing – 90% complete. (See the final truss being flown in, above, in preparation for final framing and sheathing.)

Gym: Glulam* vertical components going in.

Dorm: fire alarm inspection anticipated, followed by insulation and drywall.

Share on FacebookTweet about this on TwitterEmail this to someone