Next Week(s)

Gym:

  • Pouring concrete floor.
  • Drying-in the roof.

Campus: Right-of-way permitting underway for natural gas main line extension.

Ongoing:

  • K-8 Schoolhouse: MEP rough-in continues through early March.
  • Music & Science Learning Center: The Design Team is working on a modified building design to reduce costs.
  • LEED Gold application process continues.