Next Week(s)

K-8 Schoolhouse: truss installation and roof framing, which are the final steps to get the building “dried in” (enclosed).

Gym: rough-in of mechanical, electrical and plumbing lines.

Dorm: completion of finishes: insulation, drywall, paint, flooring, cabinetry.

Music + Science: DAG meets 12/18 to begin design development phase.

Campus:

  • Installation of the water farm (three tanks storing 70,000 gallons of water for fire suppression and domestic water use).
  • Trenching, laying pipe and backfilling natural gas infrastructure.

Ongoing:

  • Design review of the FF&E (furniture, fixtures and equipment).
  • LEED Gold application process.
  • Fundraising for Phase II: $3.75M goal.