Last Week(s)


K8 Schoolhouse:

  • Radiant heat and other sub-slab utilities installed.
  • Slab-on-grade concrete poured.
  • Perimeter wall framing completed.

Gym: Concrete poured for foundation footing.

Dorm: Final permit pulled for fire sprinkler and alarm.

New water main installed from the well to the water farm.