Last Week(s)
January 28, 2015
K-8 Schoolhouse:
- Roof sheathing and framing completed.
- Air handling unit delayed; anticipated for this week.
Gym: Glulam vertical components installed. (See above.)
Dorm:
- Insulation and drywall mounted.
- Three inspections passed: fire alarm, insulation and drywall.
Campus: Earthmoving permit received for natural gas mainline extension.