Last Week(s)

Gym_glulam

K-8 Schoolhouse:

  • Roof sheathing and framing completed.
  • Air handling unit delayed; anticipated for this week.

Gym: Glulam vertical components installed. (See above.)

Dorm:

  • Insulation and drywall mounted.
  • Three inspections passed: fire alarm, insulation and drywall.

Campus: Earthmoving permit received for natural gas mainline extension.