Last Week(s)

K-8 Schoolhouse:

  • after air handling unit is installed Friday, roof sheathing will be finalized.
  • “dry-in” (enclosure from elements) will be completed, readying school for MEP installations.

Gym: wall and roof framing begins.

Dorm: finishes in the works (insulation/drywall/paint/flooring/cabinetry).

Campus:

  • installation of the water farm by end of January.
  • permitting underway for natural gas main line extension.

Ongoing:

  • Music & Science Learning Center: scrubbing the budget on first round of design.
  • Design review of the FF&E (furniture, fixtures and equipment) nearing completion.
  • LEED Gold application process.