Last Week

Upper Lot Fencing

Staff parking lot was finished with recycled asphalt and then fenced.

Two concrete retaining walls for the K-8 building were poured.

Design Team responded to the State with building permit review comments and is awaiting the final permit. (The project’s five other permits are in and being exercised.)

Shallow utilities, including telephone and data cabling, were installed.

Electrical and fire alarm systems were set up in the modular classroom.