Is there a phased plan or do we build this all at once?

Yes, there is a phased plan:

Preparation: Spring 2013-Spring 2014: Central septic and intersection improvements at base of drive; bid out for a project manager; bid out for architect; host community design meetings; bid out for general contractor; develop construction drawings and engineering.

Phase 1: Spring 2014-Fall 2015: Deconstruct the gym, which clears the site for the new school building; break ground on main building while ACS continues in the original building.

Phase 2: Summer 2015: New gym and schoolhouse open; work begins on renovation of original building.

Posted in: ABOUT CONSTRUCTION