Welcome to the ACS Blog

Next Week(s)

October 21, 2014

Insulating and hanging drywall in the Dorm. Trenching new natural gas service line. Roughing-in the Dorm fire alarm, sprinkler system and PV. Installing radiant heat in the K-8 building. Pouring slab-on-grade concrete for the K-8. Ongoing: Design review of the FF&E (furniture, fixtures and equipment) Design of Music + Science learning center LEED Gold application process Fundraising ($3,705,123 to go by December 31; $9.38M completed).

Last Week

October 3, 2014 K8_Foundation Perimeter

K-8 building perimeter foundation was completed. The State issued final building permit. The design of the old school (new music building) kicked off with a DAG meeting. Century Link (finally) moved a proprietary pedestal, allowing for foundation excavation of the gym to begin.

This Week

October 3, 2014 K-8_Trenching Sub Slab Utilities

Sub-slab utility installation for the K-8 building commenced. Gym foundation excavation began. Dorm fire alarm, fire sprinkler and PV rough-in were installed. Work on the new water main, from the well to the water farm, got underway.

« First‹ Previous456789101112Next ›Last »