November 20, 2014 RadiantFloorHeating_Framing

K8 Schoolhouse: Radiant heat and other sub-slab utilities installed. Slab-on-grade concrete poured. Perimeter wall framing completed. Gym: Concrete poured for foundation footing. Dorm: Final permit pulled for fire sprinkler and alarm. New water main installed from the well to the water farm.

Last Week

October 21, 2014 Sub-slab K8

Sub-slab utilities installed for the K-8 building. K-8 foundation waterproofed and backfilled. Gym foundation excavation completed. Steel and other structural components purchased. Order placed for air handlers, boilers and other major HVAC.

This Week

October 21, 2014 Gym Foundation

Pouring gym foundation concrete. Installing the new water main from the well to the water farm. Prepping slab-on-grade for K-8 building.