December 10, 2014 Build Team

(Hard) hats off to our Build Team, whose leadership we are grateful for (left to right): Andy Halminski, Evans Chaffee Construction Group (ECCG) Chris Penney, Consilium Partners John Fitzgerald, ECCG Matt Feuer, ECCG

This Week

November 20, 2014 Slab3

K8 Schoolhouse: Prepping for installation of steel columns and beams. Framing interior walls. Curing* concrete for K8 slab-on-grade. Gym: Pouring foundation walls. Dorm: Installing fire alarm and fire sprinkler. Submitting documents for natural gas permit.

Next Week(s)

November 20, 2014

Gym: Foundation backfill, then framing. Dorm: Finishes, including insulation and drywall. Ongoing: Steel and framing of K8 schoolhouse. Design of Music + Science learning center. Design review of the FF&E (furniture, fixtures and equipment). LEED Gold application process. Fundraising ($3,705,123 to go by December 31; $9.38M completed).