December 10, 2014 Gym_Foundation

K-8 Schoolhouse: Prep for steel work. Samples of furniture on site for staff and students to test-drive. Gym: foundation concrete completed. (See form being stripped above.) Music + Science: schematic design completed. Campus: Hard Hat Tours began (continuing through 12/19).

This Week

December 10, 2014 SteelBeams

K-8 Schoolhouse: steel erection and interior wall framing continuing. Gym: backfilling foundation. Dorm: fire sprinkler and fire alarm work ongoing. Campus: submitting documents for natural gas permit.

Next Week(s)

December 10, 2014

K-8 Schoolhouse: truss installation and roof framing, which are the final steps to get the building “dried in” (enclosed). Gym: rough-in of mechanical, electrical and plumbing lines. Dorm: completion of finishes: insulation, drywall, paint, flooring, cabinetry. Music + Science: DAG meets 12/18 to begin design development phase. Campus: Installation of the water farm (three tanks storing 70,000 gallons of water for fire suppression and domestic water use). Trenching, laying pipe and backfilling natural gas infrastructure. Ongoing: Design review of the… Read More »

‹ Previous123456789Next ›Last »