Welcome to the ACS Blog

Next Week

August 22, 2014 ACS_Circulation Map-sm

Gym and K-8 building foundation work will continue. Playing field will be prepared for placing sod next month. Experiential education (for the 5-8) and assessments (for the K-4) start on Monday. Check out the downloadable Circulation Guide and Map for how to safely approach, park and navigate the new campus layout. Ongoing: Subcontractors submitting material samples for review and approval by the Design Advisory Group in early September LEED Gold application process Fundraising: $3,740,000 to go, $9.36M completed

Last Week

July 23, 2014 Gym Demo

Gym demolition: building deconstructed and materials sorted for recycling. Key subcontractors approved, including roofing and metal siding (Pacific Sheet Metal, Carbondale); mechanical, electrical and plumbing (Climate Control Company, Glenwood Springs), and electrical (Durgin Electric, Carbondale). Topsoil stripping and stockpiling completed. Additional permits received: mobile classroom and foundation.

This Week

July 23, 2014 Dorm_Demo

Sitework continues for parking lot and drop-off area. The State building permit review is nearly complete. The Design Team is reviewing and responding to the State’s comments. Subcontractors are submitting material samples for review and approval by the Design Advisory Group next month. Interior dorm demolition is taking place. LEED Gold application process continues. Framing materials and subcontractor to be assigned. Pitkin County BOCC finalizes the Randy Udall Energy Pioneer grant from CORE.

« First‹ Previous789101112131415Next ›Last »