Welcome to the ACS Blog

Next Week

September 3, 2014

K-8 building interior foundation concrete will commence. Design Advisory Group (DAG) resumes regular meetings on 9/8. The Design Team will present furniture, fixtures, equipment and material samples to DAG for approval. Installation of sub-slab utilities, including plumbing and sewer, in K-8 building. Sprinklers and fire alarms will be installed in dorm. Ongoing: LEED Gold application process and fundraising ($3,715,123 to go, $9.38M completed).

Last Week

August 22, 2014 Holy Cross Vaults_Installation

Despite August’s frequent rains, our project team was able to stay busy and on schedule. The earthwork subcontractor worked long days and weekends to get ready for students next week. Recently completed tasks include: Utilities installation: electrical vaults (see above), main waterline, fire hydrants and natural gas service line. Finishing of the Lower Lot and drop-off area with recycled asphalt. Interior demolition, framing and rough-in of electrical and plumbing in the Dorm. Excavation for K-8 building foundation. Installation of modular… Read More »

This Week

August 22, 2014 K8 Foundation Concrete

Concrete for the K-8 building is being poured. (See above.) The final stage of the building permit is on schedule, with Design Team having sent their response to the State yesterday. Temporary electrical and fire alarm are being installed in the modular classroom. The shallow utilities are being installed. The excavation of the gym foundation is in progress. Additional safety fencing is being set up. Final work on Upper Lot for staff parking is underway.

« First‹ Previous67891011121314Next ›Last »